Phuket’s first expressway is on the way. The planned toll road runs 34.6km with 4 lanes, in two phases, and would give the island a second north to south route alongside Thepkrasattri Road, from Mueang Mai near the airport all the way to Patong.
Phase 1: under the hill to Patong

The first phase links Kathu and Patong over 3.98km. It combines elevated road with a 1.85km tunnel under Khao Nak Kerd, the hill that separates the two and the climb every Patong driver knows. The tunnel has been narrowed to 14.2m wide and carries 4 lanes, 2 for cars and 2 for motorbikes, with a barrier between them.
Phase 2: from the airport side to Kathu

The second phase covers 30.62km from Mueang Mai, near Phuket International Airport, through Koh Kaew to Kathu. It mixes ground level road, elevated sections and a second tunnel at Khao Kamala, and joins Phase 1 with a highway service area along the way.
When it could happen
Phase 1 is due to go to the Cabinet in late 2026. If it is approved, construction could start in 2027 and take about 4 years. Tolls have been proposed at 20 baht for cars and 10 baht for motorbikes.
What it means for the island
For anyone who has crawled over the Patong hill on a busy afternoon, the appeal is obvious. A direct, high capacity route from the airport area to the west coast would change how residents, workers and visitors move around Phuket, and it is one more sign of an island investing in the way it works every day.